Reconstruction and capacity upgrade of the municipal wastewater treatment plant to 150,000 m³/day.
Equipment supplied:
- Scrapers for 40 m diameter radial secondary clarifiers, with floating solids removal, sludge sweeping system, and trough & weir system
- KPz vertical bar screens
- SP-72 grit separator
- Complete sand removal system
- ZNa wall-mounted gates
- ZPa overflow gate
- TRs screw conveyors
- TRs screw press conveyor
- Belt conveyors